[FREE IRAN Project] In The Spirit Of Cyrus The Great Views expressed here are not necessarily the views & opinions of ActivistChat.com. Comments are unmoderated. Abusive remarks may be deleted. ActivistChat.com retains the rights to all content/IP info in in this forum and may re-post content elsewhere.
|
View previous topic :: View next topic |
Author |
Message |
Liberator
Joined: 29 Aug 2003 Posts: 1086
|
Posted: Fri Aug 25, 2006 10:06 pm Post subject: Rooze Rahe Ahan - Shahrivar 4th, 2497 (Shahanshahi)/ August |
|
|
Today marks the day the "National Iranian Railroad started its work. The Railroad was built by adding a few cents of tax on sugar and sugar cube. We owe thanks to Reza Shah the Great (Pahlavi I) and the dedicated servicemen of Iran who made this project successful.
To stay up to date on events in the Iranian calendar clean from Arabo-Muslim dates and events, this calendar has been proposed as the Iranian calendar post Arabo-Muslim occupation (IRI).
Proposed Iranian Calendar:
http://www.localendar.com/public/AhreemanX
**************************************************
Wikipedia on the Trans-Iranian Railway:
http://en.wikipedia.org/wiki/Trans-Iranian_Railway
The Trans-Iranian Railway was a major railway building project started in the 1930's and finished in 1939, under the direction of the Persian monarch, Reza Shah, to construct a basic network of railways joining the capital Tehran to the Persian Gulf and Caspian Sea. The Trans-Iranian Railway was built entirely by local capital. Trans-Iranian Railway is 1394 km long.
The first lines pass though formidable mountains, and international construction firms were heavily involved in the construction. Gradients up to 1 in 36 were required, plus hillclimbing techniques such as spirals were required.
Geological challenges
All sorts of geological problems were encountered, which required abandonment of some tunnels, and realignment of the route through different terrain:
* a tunnel though a salt dome had to be abandoned, as the disrupted water table would erode away the salt.
* a tunnel commenced through apparently solid rock encountered powdery gypsum, which filled the excavation as fast as it was dug out - another abandoned tunnel.
* a tunnel through pumice, was unblastable and undigable as the picks and shovels got stuck.
* a tunnel enountered a void in the mountain, requiring a bridge in the middle of the tunnel.
* poor fresh water supplies made mixing of long-lasting mortar and concrete problematic.
The principle lines were completed ahead of schedule and under budget, with the first train arriving in Tehran in about 1940.
World War II
During World War II, the railway was a vital component of the Persian Corridor supply routes connecting the Persian Gulf to Central Asia and the Soviet Union. The line was of such importance that the Allies imported rolling stock of its own design, including diesel locomotives such as the ALCO RSD-1.
Ba Sepaas _________________ JAVID IRAN!
www.anjomane-padeshahi.org
http://aryamehr11.blogspot.com/ |
|